Author: | eehiv [ Thu Feb 28, 2013 1:29 am ] |
Post subject: | CMRR Volunteer Workdays - 3/2, 3/3 |
Saturday, March 2nd Cornell Street will open at 9am. Plans are to continue work on the new west switch. Sunday, March 3rd Cornell Street may be open on Sunday. Please call Mark Glaser or Earl Pardini to confirm. Plans are to continue work on the new west switch. Ernie Hunt Volunteer Coordinator CMRR |
Author: | eehiv [ Sun Mar 03, 2013 4:09 pm ] |
Post subject: | CMRR Work Report - 3/2, 3/3 |
Saturday, March 2nd On Saturday in Kingston, a large crew turnout resulted in work on both the Cornell Street west yard switch and track expansion west of C-9. At Cornell St., all remaining switch timbers were installed including switch stand headblocks. Closure as well as siding rail connections to the frog were made, and rail was spiked to the new timbers. http://photos.greatrails.net/s/?p=206953 http://photos.greatrails.net/s/?p=206965 http://photos.greatrails.net/s/?p=206966 In the afternoon, working west of the newly opened Esopus Creek Bridge, crews removed 14 old ties and dug out 6 cribs despite partially frozen ground. All equipment west of C-9 including the car mover was successfully restarted. http://photos.greatrails.net/s/?p=206954 Participating were Earl Pardini, George Peck, Walt Otto, Dave Hilliard, Art Vogel, Mark Glaser, Thom Johnson, Tony Bocchino, Freddie Rasmussen and new volunteer Jarrett May. Sunday, March 3rd. Cornell Street was closed. Ernie Hunt Volunteer Coordinator CMRR |
Author: | eehiv [ Thu Mar 07, 2013 12:56 am ] |
Post subject: | CMRR Volunteer Workdays - 3/9, 3/10 |
Saturday, March 9th Cornell Street will open at 9am. Plans are to continue work on the new west switch. Sunday, March 10th Cornell Street may be open on Sunday. Please call Mark Glaser, George Peck or Earl Pardini to confirm. Plans are to continue work on the new west switch. Ernie Hunt Volunteer Coordinator CMRR |
Author: | eehiv [ Mon Mar 11, 2013 12:11 am ] |
Post subject: | CMRR Work Report - 3/9, 3/10 |
Saturday, March 9th Saturday at Cornell St. work continued on the new west switch. Closure rail segments were cut to size, drilled and bolted to the points. The spread was set on the north (diverging) closure rail and three ties changed out just before the headblocks. The subgrade for the link to the storage siding was leveled and 12 ties were laid in and positioned. Miscellaneous switch OTM was gathered and organized. Today's crew included: Earl Pardini, George Peck, Dave Hilliard, Jarrett May, Jim Bruck, and Mark Glaser. http://photos.greatrails.net/s/?p=207132 http://photos.greatrails.net/s/?p=207133 http://photos.greatrails.net/s/?p=207134 http://photos.greatrails.net/s/?p=207135 Sunday, March 10th Sunday, more progress was made today on the switch project @ Cornell St. The south stockrail lead was bolted to the main after hard spiking all new ties inserted yesterday west of the switch entrance. Braces,slide plates and dividers were installed on and under the north stockrail and adjacent spaces on the north point and closure rail. Today's crew included George Peck and Mark Glaser. Ernie Hunt Volunteer Coordinator CMRR |
Author: | eehiv [ Thu Mar 14, 2013 12:52 am ] |
Post subject: | CMRR Volunteer Workdays - 3.16, 3/17 |
Saturday, March 16th Cornell Street will open at 9am. Plans are to continue work on the new west switch. Sunday, March 17th Cornell Street will open at 10:30am. George Peck plans to continue work on the new west switch. Ernie Hunt Volunteer Coordinator CMRR |
Author: | eehiv [ Mon Mar 18, 2013 1:12 am ] |
Post subject: | CMRR Work Report - 3/16, 3/17 |
Saturday, March 16th At Cornell St. on Saturday, work on the west switch continued. The north stockrail was fully spiked, and the north closure rail spiked to it's connection with the frog after proper offsets were laid in from the north mainline rail. Twenty additional storage siding connector track ties were positioned. Ties now stretch from the new switch to where the storage track terminates at the soon to be removed telephone pole guy wire. Today's switch crew included Earl Pardini, John Patane, Art Vogel, Thom Johnson, George Peck, Jarrett May, Jim Bruck, Will Wilsey, and Mark Glaser. http://photos.greatrails.net/s/?p=207297 http://photos.greatrails.net/s/?p=207298 http://photos.greatrails.net/s/?p=207299 http://photos.greatrails.net/s/?p=207300 Sunday, March 17th On Sunday, the switch crew installed slide plates and braces on the south stock rail and straight closure rail. Switch clip bolts were renewed, long throw-rod installed, and all frog hookplates spiked. The gauge was set between the curved closure and south stockrail. The first full length of siding connector track was spiked; corresponding field rail gauged and tacked. Working today were Earl Pardini, George Peck, Jim Bruck, Gary Lowe, Alex Sorenson, and Mark Glaser. http://photos.greatrails.net/s/?p=207301 http://photos.greatrails.net/s/?p=207302 http://photos.greatrails.net/s/?p=207303 http://photos.greatrails.net/s/?p=207304 Ernie Hunt Volunteer Coordinator CMRR |
Author: | eehiv [ Wed Mar 20, 2013 11:48 pm ] |
Post subject: | CMRR Volunteer Workdays - 3/23, 3/24 |
Saturday, March 23rd Cornell Street will open at 9am. Plans are to continue work on the new west switch and siding track. Sunday, March 24th Cornell Street will open at 10:00am. Plans to finish work on the new west switch and siding track. Ernie Hunt Volunteer Coordinator CMRR |
Author: | eehiv [ Sun Mar 24, 2013 11:27 pm ] |
Post subject: | CMRR Work Report - 3/23, 3/24 |
Saturday, March 23rd On Saturday, at Cornell St., track crews positioned the west end switch stand, installed the short throw rod, and tamped all straight rail sections of the new turnout. All rails on the connection to the storage siding were bolted up and plated after a short length on the south side was cut and drilled. Working Saturday were: Earl Pardini, George Peck, Ernie Hunt, Art Vogel, Jim Bruck, Will Wilsey, Neil Remson, Steve Gollow, Jarrett May, Dick Wilhelm, and Mark Glaser http://photos.greatrails.net/s/?p=207418 http://photos.greatrails.net/s/?p=207419 http://photos.greatrails.net/s/?p=207420 http://photos.greatrails.net/s/?p=207421 http://photos.greatrails.net/s/?p=207422 Sunday, March 24th On Sunday, the switch crew fully spiked 37 ties on the connector track and temporarily connected the lead to the existing storage siding. All tie cribs were backfilled and areas adjacent to the switch were cleaned and regraded. Todays crew included: Steve Gollow, Russell Nelson, Neil Remson, Jim Bruck, John Patane, and Mark Glaser. Ernie Hunt Volunteer Coordinator CMRR |
Author: | eehiv [ Tue Mar 26, 2013 12:03 am ] |
Post subject: | CMRR Volunteer Workdays - 3/30, 3/31 |
Saturday, March 30th On Saturday, work will resume on extending our trackage west of C9. Crews will meet at 9am at Cornell Street, and move out west of C9 shortly after. George Peck will also lead a crew starting at Andrew's Lane at 9am. He will be doing some finish work on the Longyear siding and clearing culverts and debris from the mainline. Sunday, March 31st No crews scheduled due to Easter. Ernie Hunt Volunteer Coordinator CMRR |
Author: | eehiv [ Tue Apr 02, 2013 12:20 am ] |
Post subject: | CMRR Work Report - 3/29, 3/30 |
Friday, March 29th John Patane, George Bain and Steve Gollow worked at Cornell Street Friday. They secured the storage siding for the main, switched out the train so the side dump is east out, cleaned the bank along the Wonderly's building ( tie cart, brush, OTM, ext.), cleaned brush, graded, and started to place the remaining bridge timbers and blocks west of the tie pile and excavated and graded the relocation of the east end of the storage siding. Saturday, March 30th In Kingston, crews worked to reopen the Westbrook Lane, Fair St., and Washington Avenue crossings removing asphalt and other debris obstructing the flange ways as the scarifier was moved west. In the afternoon, west of C-9, the track was inspected to Rte. 209 noting winter damage, and a backhoe was used to clear brush at several locations to open work space for track crews. The car mover's compressor was repaired for later use with the pneumatic spike hammer. Track workers inserted eight ties fully under the rail, seven partially, and spiked four. Participating today were; Steve Gollow, Dick Wilhelm, George Bain, Raphael Demeglio, Peter Fluchere, and Mark Glaser. At Andrew's Lane, George Peck led a crew consisting of Art Vogel and Dave Heick. They restarted all equipment that had been in storage, and spread ballast over the new siding. They also installed permanent comp bars for the new siding at Longyear's. Ernie Hunt Volunteer Coordinator CMRR |
Author: | J3a-614 [ Wed Apr 03, 2013 9:10 pm ] |
Post subject: | Re: Catskill Mountain Railroad News - 2013 |
I'll confess, I don't always follow this, partially because I live a good ways off in West Virginia, but let me tip the hat to you for the slow work you've done for years and years--"brick by boring brick"--against all sorts of odds, including some people who are rather hostile to you: http://www.woodstockx.com/2013/03/31/ra ... ail-trail/ http://www.dailyfreeman.com/articles/20 ... 395557.txt http://www.woodstockx.com/2013/03/04/letters-228-36/ http://www.dailyfreeman.com/articles/20 ... 664898.txt http://www.catskillmtrailroad.com/ How do you go on holding those guys at bay? |
Author: | eehiv [ Thu Apr 04, 2013 12:16 am ] |
Post subject: | Re: Catskill Mountain Railroad News - 2013 |
This has been going on for 30 years. EH |
Author: | eehiv [ Thu Apr 04, 2013 12:17 am ] |
Post subject: | CMRR Volunteer Workdays - 4/6, 4/7 |
Saturday, April 6th On Saturday, Mark Glaser will lead a crew to insert ties west of Bridge C9. They will start at Cornell Street at 8am and move to the bridge around 9am. If you come after 9am head straight for the work area west of C9 (can be reached from 209). Also on Saturday, George Peck will lead a crew that will meet at Andrew's Lane at 9am. Goal will be to complete the siding at Longyear's and place it into service for use by the work train. Sunday, April 7th On Sunday, Mark Glaser will lead a crew to continue inserting ties west of Bridge C9. They will start at Cornell Street yard at 10am and move to the worksite west of the bridge about 11am. Ernie Hunt Volunteer Coordinator CMRR |
Author: | eehiv [ Tue Apr 09, 2013 12:09 am ] |
Post subject: | CMRR Work Report - 4/6, 4/7 |
Saturday, April 6th On Saturday, we had several crews working. In Phoenicia, George Peck, Art Vogel and Neil Remsen cleared culverts and plated and partially spiked Longyear siding. Dave Heick helped later in the day, and John Patane and I stacked rail. At Mt. Tremper, Al Johnson and John Pickett finished putting away the Christmas decorations. In Kingston on Saturday, crews working west of C-9 fully inserted 22 ties, 10 were tacked to hold gauge. Electrical repairs to the car mover and backhoe were successfully completed. Saturday's crew included Earl Pardini, Steve Gollow, Al Schoessow, Peter Fluchere, Ron Epstein, Russell Hallock, and Mark Glaser. http://photos.greatrails.net/s/?p=207723 http://photos.greatrails.net/s/?p=207724 Sunday, April 7th On Sunday, track work west of C-9 continued. 45 ties were inserted and over 50 fully spiked. As of today, the full length of the Kingston Passenger Shuttle can be accomodated west of the bridge, and the track has been safety tied to MP 5.21, about 1/2 way between Bridge C9 and Route 209. Participating today were; Earl Pardini, Al Schoessow, Steve Gollow, Ron Epstein, Raphael Demeglio, Bob Blake, and Mark Glaser. In Phoenicia, George Peck and Neil Remsen completed spiking ties in Longyear siding, and John Patane finished rail stacking. http://photos.greatrails.net/s/?p=207774 http://photos.greatrails.net/s/?p=207775 Ernie Hunt Volunteer Coordinator CMRR |
Author: | eehiv [ Wed Apr 10, 2013 11:16 pm ] |
Post subject: | CMRR Volunteer Workdays - 4/13, 4/14 |
Saturday, April 13th Saturday we will have two crews working. In Kingston, crews will continue trackwork to reach cars on 209. Meet Cornell St. Sat. 8am, Sun. 9am-those arriving later in the day please go directly to work site. Park @ Trailway's or walk in from cars @ 209. All extra hands appreciated as we will be working backhoe only pending scarifier repair. In Mt. Tremper, George Peck will continue work completing Longyear's siding. He will start there at 9am. Sunday, April 14th In Kingston, crews will meet at Cornell Street at 8am and move to 9am at the work site east of 209. In Mt. Tremper, George Peck will continue work on the Longyear siding starting at 10am. In Shokan, Paul Sternitzke and I will lead a crew cutting west of Shokan starting at 11am. Contact me if you want to join us. Ernie Hunt Volunteer Coordinator CMRR |