Right of way clearing on the WW&FRy.
http://www.rypn.org/forums/viewtopic.php?f=1&t=41600
Page 1 of 1

Author:  b. barry [ Sat Jan 27, 2018 5:50 am ]
Post subject:  Right of way clearing on the WW&FRy.

Pictures of museum volunteers clearing the right of way of trees for the WW&FRy's Mountain Extension. The Mountain Extension will extend the main line north approximately 3/4's of a mile and include the installation of the rebuilt Boston and Maine RR covered pony truss bridge over Trout Brook. Additional tree clearing is being done at the bridge site and on the grade coming into the bridge site from RT. 218 to allow access into the bridge site to drive piles and put in the approach spans. Alan Downey and Jason Lamontagne supplied some of the photos..

Here's a map Ed Lecuyer made of the Mountain Extension and a quote from Ed on the current work schedule for the southern end of Mountain Extension.

Image

Track ends at Location 1; the tree that was blocking the ROW just south of Location 1 was removed on 1/20/18, then skidded out using #9.

Trees have been (or are being) cleared from Locations 1 to 4 and Location 8. We are waiting to remove trees at Location 6 (Section 3) due to permitting. Trees have also been cleared at Locations 13-17.

Goal for spring/summer: Repair ROW up to Location 9.
Goal for Fall Work Weekend: Lay track up to Location 9 (1300 feet from Location 1)."

The following pictures are of the blow down tree being removed by hand saw and no. 9 in the cut just south of location # 1.

Image

Image

Image

Image

Tree clearing pictures from the last Saturday.

Looking south towards the current end of track through section 3 where we are waiting on a permit to work on the right of way.

Image

Image

The following pictures are right around section 8 on the map.

Image

Image

Image

Image

Image

This is location 4 where the small landside has to be fixed. You can see the missing road bed behind the fire.

Image

The slide in the road bed is in the foreground looking south.

Image

Turned around looking north from the previous picture.

Image

Right around location 2 looking north.

Image

A little north of location 3. The people in the background are at location 4 the slide.

Image

Looking north down the right of way around the curve between locations 8 and 9.

Image

Lunch time about a 100' north of the current of track.

Image

Train coming into Top of the Mountain to pick up the cutting crew Saturday evening

Image

Image

A couple more of the Saturday crew at work.

Image

Image

Image

Saturday's engine crew putting away coach 8.

Image

The weekday crew at work.

Image

Image

Image

Image

Image

Image

Work train for the weekday crew parked at the current end of track.

Image

Author:  Rick Rowlands [ Sat Jan 27, 2018 10:46 am ]
Post subject:  Re: Right of way clearing on the WW&FRy.

I remember when not too long ago the goal was to reach Top of Mountain. Now you are accelerating down the other side!

Why does Maine have to be so far away from Ohio? Oh well, maybe I'll get up there sometime this year.

Author:  Frisco1522 [ Sat Jan 27, 2018 11:41 am ]
Post subject:  Re: Right of way clearing on the WW&FRy.

You folks amaze me! All so well done too. Onward and upward.

Author:  Steve B [ Sat Jan 27, 2018 12:34 pm ]
Post subject:  Re: Right of way clearing on the WW&FRy.

What you are doing there is incredible to me. The dedication and perseverance should be a model for all groups.

Keep up the great work!

Steve

Author:  Joe Magruder [ Sat Jan 27, 2018 1:31 pm ]
Post subject:  Re: Right of way clearing on the WW&FRy.

Are the permits technical or will they require contentious public hearings?

Author:  b. barry [ Sun Jan 28, 2018 1:05 am ]
Post subject:  Re: Right of way clearing on the WW&FRy.

Joe Magruder wrote:
Are the permits technical or will they require contentious public hearings?


Just an enviromental permit for working within 250' of Trout Brook. Trout Brook has a bend that swings in close to the right of way at that point.

Author:  elecuyer [ Sun Jan 28, 2018 11:26 am ]
Post subject:  Re: Right of way clearing on the WW&FRy.

Joe Magruder wrote:
Are the permits technical or will they require contentious public hearings?

To expand on what Brendan said, a local public meeting with the Alna town planning board was required for the placement of the bridge. The planning board reviewed the plans thoroughly and with the support voiced from the abutter (Midcoast Conservancy - a regional land trust/conservationist group) voted unanimously in favor of the project.

Author:  RookieFireman [ Mon Jan 29, 2018 7:34 pm ]
Post subject:  Re: Right of way clearing on the WW&FRy.

Great work! This railroad/group never ceases to amaze me. I hope to make it up there one day.

Was #9 steamed up just for the purpose of transporting the crew and/or tools?

Author:  elecuyer [ Mon Jan 29, 2018 10:50 pm ]
Post subject:  Re: Right of way clearing on the WW&FRy.

RookieFireman wrote:
Was #9 steamed up just for the purpose of transporting the crew and/or tools?


Pretty much, yes. One of the days we also were testing the still-under-development automatic vacuum brake system on the coach and the corresponding control stand in #9. We do not want to operate trains along the 3% grade of the "Mountain Extension" for the general public without automatic brakes on the train.