 Post subject: J&L 58's Boiler Passes Hydro Test
PostPosted: Fri Mar 09, 2018 5:26 pm 

Joined: Thu Sep 22, 2011 4:29 pm
Posts: 1899
Location: Youngstown, OH
J&L 58's boiler has passed it's hydro test today and will soon be moved back to Youngstown for the final assembly of the locomotive. We are still planning to have the 58 operational by June and possibly sooner if the reassembly goes without much incident.


Attachments:
29025778_10208804937160355_5529958573715062627_n.jpg
29025778_10208804937160355_5529958573715062627_n.jpg [ 138.61 KiB | Viewed 9761 times ]
28870160_10208804937480363_2748958263438218871_n.jpg
28870160_10208804937480363_2748958263438218871_n.jpg [ 114.25 KiB | Viewed 9761 times ]
28872303_10208804936640342_4889125042657855738_n.jpg
28872303_10208804936640342_4889125042657855738_n.jpg [ 119.79 KiB | Viewed 9761 times ]

_________________
From the desk of Rick Rowlands
inside Conrail caboose 21747
Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Fri Mar 09, 2018 5:34 pm 

Joined: Thu Feb 27, 2014 10:08 am
Posts: 705
You mean I have to drive all the way out to OH again to see this?!? Great news, Rick. You show incredible endurance and enviable organizational skills. Best of luck getting it all back together. When are you targeting to complete your planned track extensions?


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Fri Mar 09, 2018 6:46 pm 

Joined: Thu Sep 22, 2011 4:29 pm
Posts: 1899
Location: Youngstown, OH
Building track and cars are the next two things that will be getting my attention. I think I can get the next 150 feet of mainline and the first switch done by June.

_________________
From the desk of Rick Rowlands
inside Conrail caboose 21747


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Fri Mar 09, 2018 6:47 pm 

Joined: Sun Aug 22, 2004 11:26 am
Posts: 4642
Location: Maine
Makes me proud to wear my J&L #58 Porter tee shirt!

Rick, you make preservation look easy!

_________________
"It's only impossible until it's done." -Nelson Mandela


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Sat Mar 10, 2018 10:06 am 

Joined: Thu Sep 22, 2011 4:29 pm
Posts: 1899
Location: Youngstown, OH
You give me too much credit! It is all just smoke and mirrors. The 58 is actually an HOn30 model that through the magic of Photoshop looks real!

Here it is without all the "Movie Magic"! :-)


Attachments:
2018-02-16 21.13.05 small.jpg
2018-02-16 21.13.05 small.jpg [ 23.51 KiB | Viewed 9303 times ]

_________________
From the desk of Rick Rowlands
inside Conrail caboose 21747
Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Sat Mar 10, 2018 2:57 pm 

Joined: Sun Sep 05, 2004 9:48 am
Posts: 1531
Location: Byers, Colorado
Congratulations, Brother Rowlands !!!

Were the soft plug in the crown sheet, and the washout plug in the tube sheet, original equipment, or were they your improvements ??? Thinking real hard about adding them on Audrey...

Viva J&L #58 !!!

_________________
Ask not what your locomotive can do for you,
Ask what you can do for your locomotive,

Sammy King


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Sat Mar 10, 2018 6:20 pm 

Joined: Wed Jun 26, 2013 7:20 pm
Posts: 211
Is that a couple of missing rivets at the bottom of the front tube sheet?


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Sat Mar 10, 2018 8:02 pm 

Joined: Thu Oct 08, 2015 11:54 am
Posts: 1773
Location: New Franklin, OH
Man, I wish I had half the energy and gumption you have. Can I borrow some for a few days? Maybe just fifteen minutes, even?

Nice work. Can't wait to see it run.

_________________
Eric Schlentner
Turner of Wrenches, Drawer of Things


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Sat Mar 10, 2018 8:10 pm 

Joined: Thu Sep 22, 2011 4:29 pm
Posts: 1899
Location: Youngstown, OH
QJdriver wrote:
Congratulations, Brother Rowlands !!!

Were the soft plug in the crown sheet, and the washout plug in the tube sheet, original equipment, or were they your improvements ??? Thinking real hard about adding them on Audrey...

Viva J&L #58 !!!


The soft plug is original, but the washout plug in the front tube sheet was added by JS Company to make boiler washouts a bit easier to do. It now has a total of 14 washout plugs.

_________________
From the desk of Rick Rowlands
inside Conrail caboose 21747


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Sat Mar 10, 2018 8:11 pm 

Joined: Thu Sep 22, 2011 4:29 pm
Posts: 1899
Location: Youngstown, OH
train guy wrote:
Is that a couple of missing rivets at the bottom of the front tube sheet?


That is an optical illusion.

_________________
From the desk of Rick Rowlands
inside Conrail caboose 21747


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Sun Mar 11, 2018 1:14 pm 

Joined: Sat Feb 11, 2006 10:42 am
Posts: 313
Location: Wyoming, DE
Rick,

Very impressive. The 58 has a lot of steel packed into a small package! It will be a brute!

Great work!

Sincerely,

Randy


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Mon Mar 12, 2018 2:29 pm 

Joined: Sun Sep 05, 2004 9:48 am
Posts: 1531
Location: Byers, Colorado
Rick,

You are going to have hours of fun with that washout plug on the tube sheet !!! It will be buried in crud on the smokebox side, and cemented with mud on the inside !!! I'm going to try for putting the washout plug above the waterline, so I can get above the tubes with the water hose. Of course, there ain't much room inside the smokebox on these little engines, no matter where the plug is located...

Enjoy,
Sammy

_________________
Ask not what your locomotive can do for you,
Ask what you can do for your locomotive,

Sammy King


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Mon Mar 12, 2018 4:08 pm 

Joined: Sat Feb 05, 2005 1:05 am
Posts: 470
QJdriver wrote:
Rick,

You are going to have hours of fun with that washout plug on the tube sheet !!! It will be buried in crud on the smokebox side, and cemented with mud on the inside !!! I'm going to try for putting the washout plug above the waterline, so I can get above the tubes with the water hose. Of course, there ain't much room inside the smokebox on these little engines, no matter where the plug is located...

Enjoy,
Sammy



Unless Rick is going to use RO water, the boiler needs regular washouts during operation and before any layup periods. The smokebox should be washed of soot/crud with every internal boilerwash. It will be a lot harder to get the mud out of the belly without the plug under the tube bundle in the front sheet. I always thought that "hours of fun" was the whole purpose of playing with steam!?!


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Tue Mar 13, 2018 1:42 pm 

Joined: Thu Sep 22, 2011 4:29 pm
Posts: 1899
Location: Youngstown, OH
I doubt that the plugs will remain undisturbed for long enough to become a problem. Regular boiler washouts will assure that the plugs remain limber. Key-Tite also helps!

_________________
From the desk of Rick Rowlands
inside Conrail caboose 21747


Offline
 Profile  
 
 Post subject: Re: J&L 58's Boiler Passes Hydro Test
PostPosted: Tue Mar 13, 2018 5:38 pm 

Joined: Sun Sep 05, 2004 9:48 am
Posts: 1531
Location: Byers, Colorado
Well, everybody has their own idea of FUN...

I don't know how much room the #58 has under the belly plug, but I had pretty good results by poking a flexible type nozzle (like refrigeration tubing) in the belly opening, bending it just right, and shooting it at the bottom of the tube sheet to dislodge crud. On the other hand, that doesn't work so great for removing mud from the upper tube bundle. The Porter saddletankers only have plugs located up high in the backhead and firebox wrapper sheet, which doesn't work so good on the tube bundle, either. This is my reasoning for putting a plug up high on the tube sheet. Also I'm hoping to find a position where I can remove it easier. (By the way, I like the way the Chinese handle the flue sheet deposits --- with a third blow down valve located under the belly, plumbed to discharge out the fireman's side, and with linkage so the fireman can see the glass while using it.)

Anyhow, if you're lucky, maybe you can scrounge up the right attachments to turn that plug without pulling everything out of the front end every time you do a boiler wash. I know there's enough room for your head inside there, but most likely not if you're wearing a hard hat. Hope you have a thick skull...

Actually, I guess you have to pull everything out so you can brush the tubes. Hours of fun.

Give it HELL !!!

_________________
Ask not what your locomotive can do for you,
Ask what you can do for your locomotive,

Sammy King


Offline
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 15 posts ] 

All times are UTC - 5 hours [ DST ]


 Who is online

Users browsing this forum: Google [Bot], Majestic-12 [Bot] and 110 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to: