Reading T-1 No.2100
Roundhouse Work Session Report for 04.09.2016

Volunteers
The following volunteers attended Saturday’s work session:
• Matt Ash
• Stephanie Bierley
• Brody Brightwell
• Steven Harvey
• Eric Kapusta
• Chris Lairson
• Rick Owings
• Brian Tusin

Work Report
This week saw the ultrasound completed on both side sheets in the firebox. The ultrasounds testing continued into Sunday with contractor Jason Sobcznski and volunteers Brody and Chris. The white reflective 2100 lettering was removed off of both cab sides by Stephanie and Eric.

Upcoming Work Session Tasks:
The following tasks are planned for the upcoming work sessions in April including:
• Take UT readings and record for analysis.
• Cut new gaskets seats with the portable Mill Hog on the worst of the badly pitted gasket seats saving many man-hours that would otherwise take week to complete by hand. Approximately 12 of the washout plug seats will have new seats cut in this manner.
• Continue lapping the medium size washout plug gasket seats
• Reinstall washout plugs with new gaskets
• Complete an initial air test and fix all detected leaks
• Complete a hydrostatic test and fix all detected leaks
• Remove historically inaccurate red 3M adhesive reflective material from side skirts.




Upcoming Events
• We will be at Midwest Railway Historical Society’s Open House on April 16th, 2016.
• The next work session is Saturday, April 23, 2016 and starts at 9 am.
• Don’t forget to come ready to sign and complete a volunteer waiver and if you are not a member already, come prepared to fill out a membership form and be able to pay your membership dues at that time.

Image

Respectfully submitted,

Brian Tusin
Corresponding Secretary


Offline
 Profile  
 
 Post subject: Re: ASR Reading 2100 Workday Report 04/09/2016
PostPosted: Fri Apr 15, 2016 12:42 pm 

Joined: Sat Jul 16, 2011 3:12 pm
Posts: 121
Keep up the good work!

_________________
Bret Evanich


Offline
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 2 posts ] 

All times are UTC - 5 hours [ DST ]


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to: