Author: | Brian Hiscock [ Tue Feb 02, 1999 12:30 am ] |
Post subject: | Laying some track. |
Interested in knowing a 'ballpark'cost of laying about 40 miles of track with used rails and ties. This is for construction on the old Newfoundland rwy which still has the roadbed. Thanks.<br> skeezix@ns.sympatico.ca |
Author: | Gary Landrio [ Tue Feb 02, 1999 1:39 pm ] |
Post subject: | Re: Laying some track. |
First lets be clear that we are talking in Canadian dollars. To lay the narrow gauge track on an existing roadbed with a combination of relay and new ties and rail similar to what was there originally can be done for about $70 to $100 per foot. This depends on several factors including the amount of ballast/cinders available on the roadbed, the condition of bridges, and in general any needed drainage improvements.<p>Other items which add cost are rebuilding grade crossings, brush cutting and highway crossing signals.<br> garyland@stoneconsulting.com |
Page 1 of 1 | All times are UTC - 5 hours [ DST ] |
Powered by phpBB © 2000, 2002, 2005, 2007 phpBB Group http://www.phpbb.com/ |