Greetings. The Berkshire Scenic Railway Museum is in the process of restoring a Howard bell for our 1941 B&M SW-1. We are installing the original copper tubing from the top of the bell to the trunnion but are unsure of the cylindrical piece at the top? What is this and where can it be procured? Thank you!
|
||||
| Author: | Al P. [ Wed Nov 14, 2018 1:08 pm ] |
| Post subject: | Re: Howard Bell Question |
Brent, I suspect it may have been a speed control device, designed to limit the amount of air into the ringer. there are commercial units available from SMC for one, but will not be a direct replacement. |
|
| Author: | Brent S. Bette [ Thu Nov 15, 2018 9:38 pm ] |
| Post subject: | Re: Howard Bell Question |
Thank you, Al! Much appreciated. |
|