January 2, 2020 John Marino, Raphael DeMeglio, Sam Cogan, Peter Fluchere and Matt Gillis completed taking down the Polar Tent and storing materials for the next Polar Event. January 7, 2020 Sam Cogan and Dave Heick worked at Hurley Mountain Road. January 10, 2020 Earl Pardini did backhoe repairs. January 11, 2020 Earl Pardini, John Marino, Art Vogel, Vince Guido, Bryan Van Kirk and Tom Whyte moved equipment into position for the section house move. January 13, 2020 Bryan Van Kirk, Sam Cogan and Dave Heick moved engine parts from the container to the box car. January 13, 2020 Earl Pardini, Bryan Van Kirk, Art Vogel, Sam Cogan, Vince Guido, Tom Whyte, Tom Comito and Dave Heick moved the section house to its permanent location near MP 6. January 22, 2020 Bryan Van Kirk, Sam Cogan and Dave Heick did work on the 2911. January 23, 2020 Bryan Van Kirk, Sam Cogan and Dave Heick did work on the 2911. January 24, 2020 Sam Cogan and Dave Heick did work on the 2911. January 26, 2020 Bryan Van Kirk and Art Vogel worked on the crane. January 30, 2020 Bryan Van Kirk, Sam Cogan and Dave Heick did work on the 2911. Ernie Hunt Volunteer/Staff Coordinator CMRR |
|
| Author: | eehiv [ Sat Mar 21, 2020 12:14 pm ] |
| Post subject: | CMRR Work Report - February 2020 |
February 3, 2020 Sam Cogan and Dave Heick did cleanup work at the North Pole. February 5, 2020 Sam Cogan and Dave Heick worked at the North Pole. Bryan n Kirk worked on the 2918. February 7, 2020 Bryan Van Kirk, Sam Cogan, and Dave Heick worked on the 2911. February 8, 2020 John Marino, Earl Pardini, Bryan Van Kirk, Sam Cogan and Dave Hilliard switched out the work train and repaired the Trailways crossing. February 10, 2020 Sam Cogan, Dave Heick and Vince Guido removed the trailer from under the section house. February 11, 2020 Bryan Van Kirk, Sam Cogan and Dave Heick worked on the 2911. February 16, 2020 Vince Guido installed the stairs on the section house. February 20, 2020 The County issued a Certificate of Occupancy for the Section House. February 21, 2020 Sam Cogan and Dave Heick worked on the 2911. February 22, 2020 Bryan Van Kirk, Sam Cogan and Dave Heick, John Marino and Earl Pardini did work on the 2911. John Marino did a track inspection. February 24, 2020 Bryan Van Kirk, Earl Pardini, Sam Cogan and Dave Heick did work on the 2911. February 27, 2020 Sam Cogan and Dave Heick did work on the 2911. John Marino did a track inspection. February 28 2020 John Marino, Tom Whyte, Vince Guido, Sam Cogan, Martin Elbrecht, and Dave Heick did cleanup work at the Section House. February 29, 2020 John Marino, Bryan Van Kirk, Dave Hilliard, Ken Harris, Martin Elbrecht and Vince Guido moved all track materials from Hurley Mountain road to the new section house site. The section house is now in service for use by the track crews. Ernie Hunt Volunteer/Staff Coordinator CMRR |
|
| Author: | eehiv [ Sat Apr 04, 2020 10:11 am ] |
| Post subject: | CMRR Work Report - March 2020 |
March 5, 2020 Bryan Van Kirk, Art Vogel, Sam Cogan and Dave Heick worked on the 2911. March 6, 2020 Earl Pardini and John Marino did a field inspection. March 7, 2020 Sam Cogan did work in the Phoenicia yard. John Marino and Dave Hilliard did a field inspection. March 9, 2020 Sam Cogan and Dave Heick moved P72 seats stored in Phoenicia to Kingston. Vince Guido cleared brush near the section house. March 11, 2020 John Marino led a track crew consisting of Sam Cogan and Dave Heick. March 12, 2020 John Marino led a track crew consisting of Sam Cogan and Dave Heick. March 14, 2020 Vince Guido cleared brush near the section house. The CMRR held its winter rules class. No further work parties were held in March due to the current work shutdown in NY State. Ernie Hunt Volunteer/Staff Coordinator CMRR |
|
| Author: | eehiv [ Thu Aug 13, 2020 4:11 pm ] |
| Post subject: | Re: Catskill Mountain Railroad (CMRR) Discussion - 2020 |
The CMRR resumed operations last July 11th, using open flats only. Some recent photos of the CMRR: http://photos.greatrails.net/s/?p=259102 http://photos.greatrails.net/s/?p=259103 http://photos.greatrails.net/s/?p=259104 http://photos.greatrails.net/s/?p=259105 http://photos.greatrails.net/s/?p=259106 The CMRR last week brought down 2 additional flats from Phoenicia. We now have a 5 car train: https://catskillmountainrailroad.com/wp ... 48x330.jpg We are limiting capacity to 25% or 60 per train to maintain social distancing guidelines. EH |
|
| Author: | eehiv [ Sun Dec 20, 2020 2:14 am ] |
| Post subject: | Re: Catskill Mountain Railroad (CMRR) Discussion - 2020 |
CMRR Catskill Christmas Express - 19 December 2020. Train was sold out at a reduced capacity of 84 per train. https://www.youtube.com/watch?v=YwB-zovZgHQ https://www.youtube.com/watch?v=GXOJOYUv8MY http://photos.greatrails.net/s/?p=261141 http://photos.greatrails.net/s/?p=261142 http://photos.greatrails.net/s/?p=261143 http://photos.greatrails.net/s/?p=261144 |
|