 Post subject: Vulcan 1916 Rebuild
PostPosted: Sat Apr 10, 2004 4:36 pm 

In October 2003, Camp 5, Laona Northern commenced
a complete rebuild of The Vulcan 2-6-2 steam
locomotive. Extensive boiler work was required,
as was machinery rebuild, including new axels, driving boxes, wedges and all parts of the runing
gear. So far, work has progressed to the point, that things are going back together and the locomotive will be ready for it's first run in early June 2004 in Laona Wisconsin. Camp 5 is a
small tourist railroad in northern Wisconsin. See
our web site at www.camp5museum.org

roundhouse@sat-a-link.com


  
 
 Post subject: Ahhh Vulcan! *NM*
PostPosted: Sat Apr 10, 2004 6:14 pm 

superheater@rrmail.com


  
 
 Post subject: Ahhh Vulcan!
PostPosted: Sat Apr 10, 2004 6:15 pm 

> Live long and prosper!!!!!!!!!!!!!!

Its only logical!

superheater@rrmail.com


  
 
 Post subject: Re: Vulcan 1916 Rebuild
PostPosted: Sat Apr 10, 2004 9:28 pm 

> In October 2003, Camp 5, Laona Northern
> commenced
> a complete rebuild of The Vulcan 2-6-2 steam
> locomotive. Extensive boiler work was
> required,
> as was machinery rebuild, including new
> axels, driving boxes, wedges and all parts
> of the runing
> gear. So far, work has progressed to the
> point, that things are going back together
> and the locomotive will be ready for it's
> first run in early June 2004 in Laona
> Wisconsin. Camp 5 is a
> small tourist railroad in northern
> Wisconsin. See
> our web site at www.camp5museum.org

Cool. Nice freindly little operation. Now, who do we contact to encourage to repaint the equipment back into Soo Line colors? Both coaches, and two of the three cabeese are ex-Soo, with the last caboose being ex-DM&IR. I belong to the Soo Line Hist. & Tech. Society, and would be more than happy to track down the stencils.

The "circus" colors may have made sense for the tourist train years ago, but they don't even advertise the trip under the Laona & Northern name anymore.

By the way, little 4 spot was purchased new by another Wisconsin shortline, the Fairchild & Northeastern.

Dennis

dstorzek@elnet.com


  
 
 Post subject: Re: Vulcan 1916 Rebuild
PostPosted: Mon Apr 12, 2004 9:56 pm 

> In October 2003, Camp 5, Laona Northern
> commenced
> a complete rebuild of The Vulcan 2-6-2 steam
> locomotive. Extensive boiler work was
> required,
> as was machinery rebuild, including new
> axels, driving boxes, wedges and all parts
> of the runing
> gear. So far, work has progressed to the
> point, that things are going back together
> and the locomotive will be ready for it's
> first run in early June 2004 in Laona
> Wisconsin. Camp 5 is a
> small tourist railroad in northern
> Wisconsin. See
> our web site at www.camp5museum.org

I was talking to the contractor who did the boiler work on the #4. Didn't go into great detail on what had to be done. I know about some of the side sheet work and staybolts, any other info on the extent of boiler work? I have been meaning to take a drive over there to see what I could find out and maybe take some pictures, but haven't made it yet. Glad to hear the rebuild has gone well. How about some gory details for those of us who are interested? Not trying to be nosey, just genuinely interested in all steam rebuilds. Regards, John.


  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 5 posts ] 

All times are UTC - 5 hours [ DST ]


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Jump to: