 Post subject: Keokuk Union Depot Roof Restoration Resumes
PostPosted: Thu Sep 14, 2017 9:12 am 
User avatar

Joined: Sat Jan 20, 2007 5:40 pm
Posts: 418
Location: Hamilton, Illinois
After a nine-month-long hiatus in roof work due to delay in delivery of the tiles, work has resumed on restoring the roof of the Keokuk Union Depot. In 2017 the central tower was raised to its full height and tiled (viewtopic.php?f=1&t=39744&hilit=keokuk+union+depot). The roofing of both the upriver and downriver ends of the Depot is to be completed this fall.

In the first photo we see tiling going up on the bluff side of the upriver (waiting room) end. The second photo shows roof repairs under way on the downriver (express room) end after tearoff of the deteriorated asphalt shingles. The upriver end did not require the same plywood overlay after tearoff, but the roof boards on the downriver end were damaged and tiles could not be adequately attached to them, so an overlay was required.


Attachments:
File comment: Tiling commences on the upriver end.
depot_tiling_9-9-2017.jpg
depot_tiling_9-9-2017.jpg [ 147.96 KiB | Viewed 9638 times ]
File comment: Repairs to the downriver roof.
depot_roof_repair_9-11-2017.jpg
depot_roof_repair_9-11-2017.jpg [ 127.22 KiB | Viewed 9638 times ]

_________________
Richard Leonard's Rail Archive
www.railarchive.net
Offline
 Profile  
 
 Post subject: Re: Keokuk Union Depot Roof Restoration Resumes
PostPosted: Thu Sep 14, 2017 10:44 pm 

Joined: Tue Aug 02, 2005 1:25 pm
Posts: 6443
Richard -

Good to see that work is once again going forward. In one of the other threads on the Keokuk depot, there was some talk of glass windows being installed in the dormers of the central tower. Did that ever get done?

Les


Offline
 Profile  
 
 Post subject: Re: Keokuk Union Depot Roof Restoration Resumes
PostPosted: Thu Sep 14, 2017 11:15 pm 
User avatar

Joined: Sat Jan 20, 2007 5:40 pm
Posts: 418
Location: Hamilton, Illinois
Yes, Les, thanks for the reminder. That was completed in July. Here are two views of the trackside window. The opening on both track and bluff sides was originally (1891) supposed to hold a clock, but no clock was ever installed.


Attachments:
depot_round_window1_7-15-2017.jpg
depot_round_window1_7-15-2017.jpg [ 124.81 KiB | Viewed 9475 times ]
depot_round_window2_7-15-2017.jpg
depot_round_window2_7-15-2017.jpg [ 132.2 KiB | Viewed 9475 times ]

_________________
Richard Leonard's Rail Archive
www.railarchive.net
Offline
 Profile  
 
 Post subject: Re: Keokuk Union Depot Roof Restoration Resumes
PostPosted: Tue Sep 26, 2017 3:05 pm 
User avatar

Joined: Sat Jan 20, 2007 5:40 pm
Posts: 418
Location: Hamilton, Illinois
Roof tiling is progressing over the waiting room (upriver) end of the Depot. This was the view 9-26-2017.


Attachments:
Depot_Tiling_9-26-17.jpg
Depot_Tiling_9-26-17.jpg [ 114.63 KiB | Viewed 9301 times ]

_________________
Richard Leonard's Rail Archive
www.railarchive.net
Offline
 Profile  
 
 Post subject: Re: Keokuk Union Depot Roof Restoration Resumes
PostPosted: Wed Sep 27, 2017 9:46 pm 
User avatar

Joined: Sat Jan 20, 2007 5:40 pm
Posts: 418
Location: Hamilton, Illinois
More views taken today by Depot treasurer Sandra Seabold show further progress on both the upriver and downriver ends of the Depot.


Attachments:
Depot_Tiling1_9-27-17.jpg
Depot_Tiling1_9-27-17.jpg [ 107.68 KiB | Viewed 9130 times ]
Depot_Tiling2_9-27-17.jpg
Depot_Tiling2_9-27-17.jpg [ 167.13 KiB | Viewed 9130 times ]

_________________
Richard Leonard's Rail Archive
www.railarchive.net
Offline
 Profile  
 
 Post subject: Re: Keokuk Union Depot Roof Restoration Resumes
PostPosted: Mon Oct 02, 2017 11:01 am 

Joined: Sat Sep 18, 2004 1:21 pm
Posts: 487
Location: Columbus, OH
Congratulations on your progress, the station is looking great. It is a quite ornate station for its relatively small size.

_________________
Christopher D. Coleman

https://www.oldeastie.com Old Eastie: East Broad Top Homepage
https://www.febt.org Friends of the East Broad Top
https://www.eastbroadtop.com East Broad Top Railroad


Offline
 Profile  
 
 Post subject: Re: Keokuk Union Depot Roof Restoration Resumes
PostPosted: Mon Oct 02, 2017 11:54 am 
User avatar

Joined: Sat Jan 20, 2007 5:40 pm
Posts: 418
Location: Hamilton, Illinois
The Depot was built in 1891 by the five railroads then serving Keokuk, which formed the Keokuk Union Depot Company. The structure is not really that small. The upriver end is a large waiting room and ticket office. The central tower has two floors, originally a baggage room at ground level and the operator's office on the second floor. The downriver end consists of three separate express company rooms and the boiler room. For a small Midwestern city like Keokuk, the structure is of fairly good size. The cost of restoring the tile roof and the eaves, including rebuilding the peak of the central tower (truncated around 1950), will amount to about $1,250,000.00. For more information see some of our previous threads about the project:
http://www.rypn.org//forums/viewtopic.p ... ot#p236695
viewtopic.php?f=1&t=39744&p=252359&hilit=keokuk+union+depot#p252359

_________________
Richard Leonard's Rail Archive
www.railarchive.net


Offline
 Profile  
 
Display posts from previous:  Sort by  
Post new topic Reply to topic  [ 7 posts ] 

All times are UTC - 5 hours [ DST ]


 Who is online

Users browsing this forum: Google [Bot], Majestic-12 [Bot], TrainDetainer and 87 guests


You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot post attachments in this forum

Search for:
Jump to: